Wastewater Treatment Plant Biofilter
Federal contribution
$520,325
Federal share45%
of $1.1M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedSep 29, 2017
20182019
Built
Approved 3 weeks before the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Town of Lunenburg
- Construction start
- Jun 15, 2018(actual)
- Construction end
- Feb 20, 2019(actual)
Against the original forecast
- Construction start10 months lateforecast Aug 10, 2017
- Construction end13 months earlyforecast Mar 31, 2020
Also in Lunenburg
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 51825 in the federal list. How to read these figures.