Solar Energy System Including Battery Storage for Electric buses
Federal contribution
$749,830
Federal share47%
of $1.6M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 29, 2018
201820192020
Built
- Program
- Public Transit Infrastructure Fund
- Ultimate recipient
- Alberta Ministry of Transportation
- Construction start
- Aug 15, 2017(actual)
- Construction end
- Jun 30, 2020(actual)
Against the original forecast
- Construction start5 months lateforecast Mar 1, 2017
- Construction end4 weeks earlyforecast Jul 31, 2020
Also in Grande Prairie
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 51965 in the federal list. How to read these figures.