Water and Sanitary Sewer Renewal - Carleton and Portage Street

St. George, New Brunswick

completeDrinking WaterSCF
Federal contribution
$176,708
Federal share33%

of $530.1K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 30, 2019
2019
Built

Approved 18 months before the announcement.

Program
Provincial-Territorial Infrastructure Component - Small Communities Fund
Ultimate recipient
Town of St. George
Construction start
Aug 31, 2018(actual)
Construction end
Nov 1, 2018(actual)

Against the original forecast

  • Construction start3 months lateforecast Jun 4, 2018
  • Construction end5 weeks lateforecast Sep 28, 2018

Also in St. George