Extension of the bike path

Drummondville, Quebec

completeActive TransportationSCF
Federal contribution
$92,735
Federal share33%

of $278.2K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 12, 2018
20192020
Built

Approved 4 months before the announcement.

Program
Provincial-Territorial Infrastructure Component - Small Communities Fund
Ultimate recipient
City of Drummondville
Construction start
Jun 1, 2018(actual)
Construction end
Jan 21, 2020(actual)

Against the original forecast

  • Construction end16 months lateforecast Sep 28, 2018