Water and Sewer Upgrades
Conception Bay South, Newfoundland and Labrador
Federal contribution
$194,302
Federal share33%
of $583.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 6, 2018
201920202021
Built
Approved 3 months before the announcement.
- Program
- Provincial-Territorial Infrastructure Component - Small Communities Fund
- Ultimate recipient
- Town of Conception Bay South
- Construction start
- Oct 22, 2019(actual)
- Construction end
- May 24, 2021(actual)
Against the original forecast
- Construction start7 weeks lateforecast Sep 1, 2019
- Construction end7 months earlyforecast Dec 31, 2021
Also in Conception Bay South
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 52195 in the federal list. How to read these figures.