Water and Sewer Upgrades

Conception Bay South, Newfoundland and Labrador

completeDrinking WaterSCF
Federal contribution
$194,302
Federal share33%

of $583.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 6, 2018
201920202021
Built

Approved 3 months before the announcement.

Program
Provincial-Territorial Infrastructure Component - Small Communities Fund
Construction start
Oct 22, 2019(actual)
Construction end
May 24, 2021(actual)

Against the original forecast

  • Construction start7 weeks lateforecast Sep 1, 2019
  • Construction end7 months earlyforecast Dec 31, 2021