Watson Lake Lagoon Upgrades
Federal contribution
$1.6M
$1,582,470
Federal share68%
of $2.3M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 14, 2018
20192020
Built
Approved 3 months before the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Town of Watson Lake
- Construction start
- May 18, 2018(actual)
- Construction end
- Jan 3, 2020(actual)
Against the original forecast
- Construction start2 weeks lateforecast May 1, 2018
Also in Watson Lake
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 52251 in the federal list. How to read these figures.