Back to projects

Watson Lake Lagoon Upgrades

Watson Lake, Yukon

completeWastewaterCWWF
Federal contribution
$1.6M
$1,582,470
Federal share68%

of $2.3M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 14, 2018
20192020
Built

Approved 3 months before the announcement.

Program
Clean Water and Wastewater Fund
Ultimate recipient
Town of Watson Lake
Construction start
May 18, 2018(actual)
Construction end
Jan 3, 2020(actual)

Against the original forecast

  • Construction start2 weeks lateforecast May 1, 2018