Wentworth Street - Sewer Separation, Watermain, and Sanitary Sewer Renewals

Saint John, New Brunswick

completeWastewaterCWWF
Federal contribution
$192,912
Federal share50%

of $385.8K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 10, 2018
2019
Built

Approved 4 months before the announcement.

Program
Clean Water and Wastewater Fund
Ultimate recipient
City of Saint John
Construction start
Apr 23, 2019(actual)
Construction end
Jul 22, 2019(actual)

Against the original forecast

  • Construction end6 weeks earlyforecast Aug 31, 2019