Update Intake Pumps (4)
Federal contribution
$11,645
Federal share19%
of $60.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedApr 27, 2018
20192020
Built
Approved 4 weeks before the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Corporation of the Municipality of South Dundas
- Construction start
- Aug 27, 2018(actual)
- Construction end
- Dec 31, 2019(actual)
Against the original forecast
- Construction start3 months lateforecast Jun 1, 2018
- Construction end3 months lateforecast Sep 30, 2019
Also in South Dundas
- Iroquois Wastewater Treatment Plant Upgrade (South Dundas)$9.0M
- Carmen Road Watermain Rehabilitation$896.2K
- Water Tower Replacement serving the villages of Morrisburg and Iroquois approximately 2,200 households$227.6K
- Ontario Street Reconstruction of Water main & Sanitary$180.0K
- Morrisburg Pathway Rehabilitation$115.8K
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 52453 in the federal list. How to read these figures.