Back to projects

Update Intake Pumps (4)

South Dundas, Ontario

completeDrinking WaterCWWF
Federal contribution
$11,645
Federal share19%

of $60.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedApr 27, 2018
20192020
Built

Approved 4 weeks before the announcement.

Program
Clean Water and Wastewater Fund
Construction start
Aug 27, 2018(actual)
Construction end
Dec 31, 2019(actual)

Against the original forecast

  • Construction start3 months lateforecast Jun 1, 2018
  • Construction end3 months lateforecast Sep 30, 2019

Also in South Dundas

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 52453 in the federal list. How to read these figures.