Rehabilitation of the Old Batiscan Rectory
Federal contribution
$9,494
Federal share33%
of $28.5K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 27, 2018
2019
Built
Approved 3 months before the announcement.
- Program
- Provincial-Territorial Infrastructure Component - Small Communities Fund
- Ultimate recipient
- Municipality of Batiscan
- Construction start
- Sep 5, 2018(actual)
- Construction end
- Jul 25, 2019(actual)
Against the original forecast
- Construction end8 months lateforecast Nov 30, 2018
Also in Batiscan
- Program for the renewal of drinking water and wastewater pipes$398.0K
- Program for the renewal of drinking water and wastewater pipes$341.6K
- Replacement of street water main under Principale Street.$278.5K
- Program for the renewal of drinking water and wastewater pipes$139.1K
- Program for the renewal of drinking water and wastewater pipes$55.3K
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 52512 in the federal list. How to read these figures.