Rehabilitation of the Old Batiscan Rectory

Batiscan, Quebec

completeCultureSCF
Federal contribution
$9,494
Federal share33%

of $28.5K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 27, 2018
2019
Built

Approved 3 months before the announcement.

Program
Provincial-Territorial Infrastructure Component - Small Communities Fund
Ultimate recipient
Municipality of Batiscan
Construction start
Sep 5, 2018(actual)
Construction end
Jul 25, 2019(actual)

Against the original forecast

  • Construction end8 months lateforecast Nov 30, 2018

Also in Batiscan

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 52512 in the federal list. How to read these figures.