Town of Saint Andrews - Bar Road Rehabilitation
Federal contribution
$266,660
Federal share60%
of $444.4K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 30, 2019
2019
Built
Approved 12 months before the announcement.
- Program
- Rural & Northern Infrastructure Stream
- Ultimate recipient
- Town of Saint Andrews
- Construction start
- Feb 4, 2019(actual)
- Construction end
- Jul 26, 2019(actual)
Against the original forecast
- Construction start4 months lateforecast Oct 1, 2018
- Construction end9 months lateforecast Nov 1, 2018
Also in Saint Andrews
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 52619 in the federal list. How to read these figures.