Back to projects

Dolphin Extension

Victoria, British Columbia

underwayTourismNRP
Federal contribution
$1.7M
$1,708,666
Federal share33%

of $5.1M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedNov 29, 2018
today
20192021202320252027
BuiltForecast

Approved 6 weeks before the announcement.

Program
Provincial-Territorial Infrastructure Component - National and Regional Projects
Construction start
Oct 23, 2018(actual)
Construction end
Mar 31, 2027(forecast)

Also in Victoria