Holland Marsh Polder Phosphorus Reduction Facility
Bradford West Gwillimbury, Ontario
Federal contribution
$16.0M
$16,000,000
Federal share40%
of $40.0M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedNov 12, 2020
today
2021202420272030
BuiltForecast
Approved 4 weeks before the announcement.
- Program
- Disaster Mitigation and Adaptation Fund
- Ultimate recipient
- Town of Bradford West Gwillimbury
- Construction start
- Apr 1, 2027(forecast)
- Construction end
- Mar 31, 2032(forecast)