Scanlon Creek Nature Centre

Bradford West Gwillimbury, Ontario

underwayOtherGICB
Federal contribution
$4.2M
$4,174,783
Federal share60%

of $7.0M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 20, 2022
2023202420252026
BuiltForecast

Approved 3 weeks before the announcement.

Program
Green and Inclusive Community Buildings Program
Construction start
Jan 3, 2025(actual)
Construction end
Apr 30, 2026(forecast)

Against the original forecast

  • Construction start21 months lateforecast Apr 1, 2023

Also in Bradford West Gwillimbury

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 64763 in the federal list. How to read these figures.