Federal contribution
$4.2M
$4,174,783
Federal share60%
of $7.0M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 20, 2022
2023202420252026
BuiltForecast
Approved 3 weeks before the announcement.
- Program
- Green and Inclusive Community Buildings Program
- Ultimate recipient
- Lake Simcoe Conservation Foundation
- Construction start
- Jan 3, 2025(actual)
- Construction end
- Apr 30, 2026(forecast)
Against the original forecast
- Construction start21 months lateforecast Apr 1, 2023