The Morris Road Drain and Stormwater Management Facility

Bradford West Gwillimbury, Ontario

completeWastewaterCWWF
Federal contribution
$1.0M
$1,009,413
Federal share50%

of $2.0M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 24, 2017
20182019
Built
Program
Clean Water and Wastewater Fund
Construction start
Oct 10, 2017(actual)
Construction end
Dec 31, 2018(actual)

Against the original forecast

  • Construction start10 months lateforecast Dec 1, 2016
  • Construction end11 months lateforecast Jan 31, 2018

Also in Bradford West Gwillimbury

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 49643 in the federal list. How to read these figures.