Back to projects

177 Church St. Community Hub

Bradford West Gwillimbury, Ontario

completeOtherGICB
Federal contribution
$5.4M
$5,365,865
Federal share52%

of $10.3M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedOct 28, 2022
202220232024
Built

Approved 3 months before the announcement.

Program
Green and Inclusive Community Buildings Program
Construction start
Apr 1, 2021(actual)
Construction end
Oct 24, 2024(actual)

Against the original forecast

  • Construction start8 months earlyforecast Dec 7, 2021
  • Construction end2.1 years lateforecast Sep 13, 2022