177 Church St. Community Hub
Bradford West Gwillimbury, Ontario
Federal contribution
$5.4M
$5,365,865
Federal share52%
of $10.3M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedOct 28, 2022
202220232024
Built
Approved 3 months before the announcement.
- Program
- Green and Inclusive Community Buildings Program
- Ultimate recipient
- The Corporation of the Town of Bradford West Gwillimbury
- Construction start
- Apr 1, 2021(actual)
- Construction end
- Oct 24, 2024(actual)
Against the original forecast
- Construction start8 months earlyforecast Dec 7, 2021
- Construction end2.1 years lateforecast Sep 13, 2022
Also in Bradford West Gwillimbury
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 64867 in the federal list. How to read these figures.