Back to projects

Faro Public Works Building and Firehall

Faro, Yukon

completeAdministration, Emergency and Public WorksSCF
Federal contribution
$7.6M
$7,626,702
Federal share65%

of $11.8M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedFeb 15, 2021
2019202020212022
Built

Approved 2.2 years before the announcement.

Program
Provincial-Territorial Infrastructure Component - Small Communities Fund
Ultimate recipient
Town of Faro
Construction start
May 1, 2021(actual)
Construction end
Aug 31, 2022(actual)

Against the original forecast

  • Construction start4 weeks earlyforecast Jun 1, 2021
  • Construction end14 months earlyforecast Oct 31, 2023

Also in Faro

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 52976 in the federal list. How to read these figures.