Faro Water, Sewer and Road Upgrades - Phase 2
Federal contribution
$8.2M
$8,231,250
Federal share75%
of $11.0M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 11, 2019
today
202020222024202620282030
BuiltForecast
Approved 4 weeks before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- Government of Yukon
- Construction start
- Sep 17, 2021(actual)
- Construction end
- Oct 30, 2029(forecast)
Against the original forecast
- Construction start4 months lateforecast May 15, 2021
Also in Faro
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 53714 in the federal list. How to read these figures.