Faro Water, Sewer and Road Upgrades - Phase 2

Faro, Yukon

underwayWastewaterGIS
Federal contribution
$8.2M
$8,231,250
Federal share75%

of $11.0M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 11, 2019
today
202020222024202620282030
BuiltForecast

Approved 4 weeks before the announcement.

Program
Green Infrastructure Stream
Ultimate recipient
Government of Yukon
Construction start
Sep 17, 2021(actual)
Construction end
Oct 30, 2029(forecast)

Against the original forecast

  • Construction start4 months lateforecast May 15, 2021

Also in Faro

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 53714 in the federal list. How to read these figures.