Back to projects

Faro Water and Wastewater Line rehabilitation

Faro, Yukon

completeDrinking WaterCWWF
Federal contribution
$3.6M
$3,584,479
Federal share68%

of $5.3M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 22, 2016
2017201820192020
Built
Program
Clean Water and Wastewater Fund
Ultimate recipient
Town of Faro
Construction start
Jul 28, 2017(actual)
Construction end
Nov 26, 2019(actual)

Against the original forecast

  • Construction end5 weeks earlyforecast Dec 31, 2019

Also in Faro

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 46914 in the federal list. How to read these figures.