Faro pumphouses rehabilitation and reservoir upgrades

Faro, Yukon

completeDrinking WaterCWWF
Federal contribution
$4.6M
$4,590,000
Federal share75%

of $6.1M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 22, 2016
201720182019
Built
Program
Clean Water and Wastewater Fund
Ultimate recipient
Town of Faro
Construction start
Sep 11, 2017(actual)
Construction end
Sep 27, 2019(actual)

Against the original forecast

  • Construction start7 months earlyforecast Apr 1, 2018
  • Construction end5 weeks earlyforecast Oct 31, 2019