Dawson City - Turner Street Infrastructure Upgrades

Dawson City, Yukon

completeDrinking WaterGIS
Federal contribution
$1.5M
$1,509,146
Federal share75%

of $2.0M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 2, 2019
2020
Built

Approved 5 months before the announcement.

Program
Green Infrastructure Stream
Ultimate recipient
City of Dawson
Construction start
Apr 30, 2019(actual)
Construction end
Feb 27, 2020(actual)

Against the original forecast

  • Construction start2 weeks earlyforecast May 15, 2019
  • Construction end7 months earlyforecast Sep 30, 2020

Also in Dawson City

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 53601 in the federal list. How to read these figures.