Vehicle Acquisition (Phase 2)
Federal contribution
$9.5M
$9,549,510
Federal share40%
of $23.9M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 18, 2019
2020202220242026
Built
Approved 2 months before the announcement.
- Program
- Public Transit Infrastructure Stream
- Ultimate recipient
- British Columbia Transit
- Construction start
- Jun 29, 2022(actual)
- Construction end
- Mar 31, 2026(actual)
Against the original forecast
- Construction start6 months lateforecast Dec 15, 2021
Also in Victoria