Recreation and Community Development
Conception Bay South, Newfoundland and Labrador
Federal contribution
$189,721
Federal share33%
of $569.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 26, 2019
202020212022
Built
Approved 4 weeks before the announcement.
- Program
- Community, Culture & Recreation Infrastructure Stream
- Ultimate recipient
- Town of Conception Bay South
- Construction start
- Aug 17, 2020(actual)
- Construction end
- Jul 28, 2022(actual)
Against the original forecast
- Construction start4 months lateforecast Apr 15, 2020
- Construction end7 months earlyforecast Feb 28, 2023
Also in Conception Bay South
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 53970 in the federal list. How to read these figures.