Back to projects

Recreation and Community Development

Conception Bay South, Newfoundland and Labrador

completeRecreationCCRIS
Federal contribution
$189,721
Federal share33%

of $569.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 26, 2019
202020212022
Built

Approved 4 weeks before the announcement.

Program
Community, Culture & Recreation Infrastructure Stream
Construction start
Aug 17, 2020(actual)
Construction end
Jul 28, 2022(actual)

Against the original forecast

  • Construction start4 months lateforecast Apr 15, 2020
  • Construction end7 months earlyforecast Feb 28, 2023