Town of Oromocto Gateway Wetland Tourist Information and Interpretive Center

Oromocto, New Brunswick

completeTourismSCF
Federal contribution
$283,656
Federal share33%

of $851.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 14, 2019
202020212022
Built

Approved 7 weeks before the announcement.

Program
Provincial-Territorial Infrastructure Component - Small Communities Fund
Ultimate recipient
Town of Oromocto
Construction start
Mar 31, 2021(actual)
Construction end
May 19, 2022(actual)

Against the original forecast

  • Construction start6 months lateforecast Sep 16, 2020
  • Construction end3 months lateforecast Feb 28, 2022