Municipality of the County of Annapolis - Water Distribution System Upgrades: Hillside Drive
Federal contribution
$158,090
Federal share25%
of $623.2K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 20, 2019
202020212022202320242025
Built
Approved 5 weeks before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- Municipality of the County of Annapolis
- Construction start
- Oct 28, 2024(actual)
- Construction end
- Sep 26, 2025(actual)
Against the original forecast
- Construction start4 months lateforecast Jun 17, 2024
- Construction end8 weeks lateforecast Jul 31, 2025
Also in Annapolis
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 54362 in the federal list. How to read these figures.