Municipality of the County of Annapolis - Water Distribution System Upgrades: Hillside Drive

Annapolis, Nova Scotia

completeDrinking WaterGIS
Federal contribution
$158,090
Federal share25%

of $623.2K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 20, 2019
202020212022202320242025
Built

Approved 5 weeks before the announcement.

Program
Green Infrastructure Stream
Construction start
Oct 28, 2024(actual)
Construction end
Sep 26, 2025(actual)

Against the original forecast

  • Construction start4 months lateforecast Jun 17, 2024
  • Construction end8 weeks lateforecast Jul 31, 2025