Town of Greater Napanees Water Pollution Control Plant Expansion
Federal contribution
$14.0M
$14,042,397
Federal share16%
of $88.0M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 15, 2019
today
20202022202420262028
BuiltForecast
- Program
- Rural & Northern Infrastructure Stream
- Ultimate recipient
- Town of Greater Napanee
- Construction start
- Aug 14, 2023(actual)
- Construction end
- Mar 31, 2028(forecast)
Also in Greater Napanee
- HVAC/Ductwork/BAS Installation; Automatic Door Operators; Handwashing Station; Bottle Fill Station$2.1M
- Ductwork and Classroom Unit Ventilation Installation$760.0K
- Ductwork Installation; HVAC Installation; Bottle Fill Station$578.0K
- Rehabilitation of Thomas Street$463.0K
- Upgrade to the Town of Greater Napanee Wastewater Pollution Control Plant$448.0K
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 54412 in the federal list. How to read these figures.