Ductwork and Classroom Unit Ventilation Installation

Greater Napanee, Ontario

completeVentilationCVRIS
Federal contribution
$760,000
Federal share80%

of $950.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedApr 14, 2021
2022
Built

Approved 8 weeks before the announcement.

Program
COVID-19 Resilience Stream
Construction start
Jun 28, 2021(actual)
Construction end
Jan 31, 2022(actual)

Against the original forecast

  • Construction start4 months lateforecast Feb 18, 2021
  • Construction end8 weeks earlyforecast Mar 31, 2022

Also in Greater Napanee

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 58583 in the federal list. How to read these figures.