Upgrade to the Town of Greater Napanee Wastewater Pollution Control Plant
Federal contribution
$447,983
Federal share11%
of $4.2M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMay 23, 2017
201820192020
Built
Approved 2 weeks before the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Town of Greater Napanee
- Construction start
- Mar 19, 2018(actual)
- Construction end
- Dec 20, 2019(actual)
Against the original forecast
- Construction start14 months lateforecast Jan 30, 2017
- Construction end9 months earlyforecast Oct 1, 2020
Also in Greater Napanee
- Town of Greater Napanees Water Pollution Control Plant Expansion$14.0M
- HVAC/Ductwork/BAS Installation; Automatic Door Operators; Handwashing Station; Bottle Fill Station$2.1M
- Ductwork and Classroom Unit Ventilation Installation$760.0K
- Ductwork Installation; HVAC Installation; Bottle Fill Station$578.0K
- Rehabilitation of Thomas Street$463.0K
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 49194 in the federal list. How to read these figures.