Ductwork Installation; HVAC Installation; Bottle Fill Station
Federal contribution
$578,000
Federal share80%
of $722.5K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedApr 14, 2021
202220232024
Built
Approved 8 weeks before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Algonquin and Lakeshore Catholic District School Board
- Construction start
- Jun 28, 2021(actual)
- Construction end
- Dec 31, 2023(actual)
Against the original forecast
- Construction start4 months lateforecast Feb 18, 2021
Also in Greater Napanee
- Town of Greater Napanees Water Pollution Control Plant Expansion$14.0M
- HVAC/Ductwork/BAS Installation; Automatic Door Operators; Handwashing Station; Bottle Fill Station$2.1M
- Ductwork and Classroom Unit Ventilation Installation$760.0K
- Rehabilitation of Thomas Street$463.0K
- Upgrade to the Town of Greater Napanee Wastewater Pollution Control Plant$448.0K
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 58594 in the federal list. How to read these figures.