Rehabilitation of Off Lake Road Culvert
Federal contribution
$192,453
Federal share60%
of $320.8K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 25, 2020
2021
Built
Approved 3 months before the announcement.
- Program
- Rural & Northern Infrastructure Stream
- Ultimate recipient
- Township of Chapple
- Construction start
- Jun 22, 2021(actual)
- Construction end
- Jul 29, 2021(actual)