Schedule

Announced and approvedJun 7, 2021
2022
Built

Approved 3 months before the announcement.

Program
COVID-19 Resilience Stream
Ultimate recipient
Township of Chapple
Construction start
Jul 1, 2022(actual)
Construction end
Jul 29, 2022(actual)

Against the original forecast

  • Construction start12 months lateforecast Jul 1, 2021
  • Construction end6 months lateforecast Jan 21, 2022