Upgrade to main outlet pipe from Chapple Lagoon
Federal contribution
$50,000
Federal share49%
of $101.1K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMay 24, 2017
Built
Approved 3 weeks before the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Township of Chapple
- Construction start
- Nov 1, 2017(actual)
- Construction end
- Nov 15, 2017(actual)
Against the original forecast
- Construction start4 months lateforecast Jul 15, 2017
- Construction end4 months lateforecast Jul 20, 2017
Also in Chapple
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 48500 in the federal list. How to read these figures.