Chapple Water Treatment Plant Infrastructure Repairs

Chapple, Ontario

underwayDrinking WaterGIS
Federal contribution
$104,450
Federal share40%

of $261.1K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedApr 14, 2022
today
2022202420262028
BuiltForecast

Approved 6 weeks before the announcement.

Program
Green Infrastructure Stream
Ultimate recipient
Township of Chapple
Construction start
Jun 1, 2024(actual)
Construction end
Dec 31, 2027(forecast)