Rehabilitation of the Access Road to Three First Nation Communities
Federal contribution
$825,784
Federal share75%
of $1.1M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 15, 2020
20212022
Built
Approved 8 weeks before the announcement.
- Program
- Rural & Northern Infrastructure Stream
- Ultimate recipient
- Naotkamegwanning First Nation
- Construction start
- Apr 19, 2022(actual)
- Construction end
- Sep 30, 2022(actual)
Against the original forecast
- Construction end2 months earlyforecast Nov 30, 2022
Also in Naotkamegwanning