Repairs and Upgrades at Wastewater Treatment Plant
Federal contribution
$60,488
Federal share50%
of $121.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedOct 10, 2017
2017201820192020
Built
Approved 4 months before the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Naotkamegwanning First Nation
- Construction start
- Jun 30, 2016(actual)
- Construction end
- Mar 31, 2020(actual)
Against the original forecast
- Construction start7 months earlyforecast Feb 1, 2017
Also in Naotkamegwanning
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 50365 in the federal list. How to read these figures.