Wastewater Plant Replacement

Naotkamegwanning, Ontario

underwayWastewaterGIS
Federal contribution
$2.2M
$2,221,200
Federal share75%

of $3.0M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 18, 2021
202120222023202420252026
BuiltForecast

Approved 4 months before the announcement.

Program
Green Infrastructure Stream
Construction start
Apr 8, 2024(actual)
Construction end
Jun 26, 2026(forecast)

Also in Naotkamegwanning

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 57323 in the federal list. How to read these figures.