Back to projects

Repairs at Water Treatment Plant

Naotkamegwanning, Ontario

completeDrinking WaterCWWF
Federal contribution
$22,500
Federal share50%

of $45.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedOct 10, 2017
20182019
Built

Approved 4 months before the announcement.

Program
Clean Water and Wastewater Fund
Construction start
Oct 13, 2017(actual)
Construction end
May 8, 2019(actual)

Against the original forecast

  • Construction start8 months lateforecast Feb 1, 2017
  • Construction end14 months lateforecast Mar 1, 2018

Also in Naotkamegwanning