completeActive TransportationCCRIS
Federal contribution
$73,204
Federal share40%

of $183.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 3, 2020
20212022
Built

Approved 4 months before the announcement.

Program
Community, Culture & Recreation Infrastructure Stream
Ultimate recipient
Nelson Cycling Club
Construction start
Jun 5, 2020(actual)
Construction end
Aug 31, 2022(actual)

Against the original forecast

  • Construction end2 months earlyforecast Nov 12, 2022