Fort St. John - Festival Plaza
Fort St. John, British Columbia
Federal contribution
$1.1M
$1,050,300
Federal share40%
of $2.6M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 3, 2020
2021
Built
Approved 4 months before the announcement.
- Program
- Community, Culture & Recreation Infrastructure Stream
- Ultimate recipient
- City of Fort St. John
- Construction start
- Jun 26, 2020(actual)
- Construction end
- Jun 24, 2021(actual)
Against the original forecast
- Construction start3 months lateforecast Apr 1, 2020
- Construction end6 months lateforecast Dec 13, 2020