Fort St. John - Festival Plaza

Fort St. John, British Columbia

completeCultureCCRIS
Federal contribution
$1.1M
$1,050,300
Federal share40%

of $2.6M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 3, 2020
2021
Built

Approved 4 months before the announcement.

Program
Community, Culture & Recreation Infrastructure Stream
Ultimate recipient
City of Fort St. John
Construction start
Jun 26, 2020(actual)
Construction end
Jun 24, 2021(actual)

Against the original forecast

  • Construction start3 months lateforecast Apr 1, 2020
  • Construction end6 months lateforecast Dec 13, 2020