Whiskey Jack Nordic Ski Club Society - Day Lodge

Fort St. John, British Columbia

completeRecreationCCRIS
Federal contribution
$219,778
Federal share40%

of $549.4K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 3, 2020
20212022
Built

Approved 8 weeks before the announcement.

Program
Community, Culture & Recreation Infrastructure Stream
Construction start
Sep 7, 2021(actual)
Construction end
Mar 31, 2022(actual)

Against the original forecast

  • Construction start3 months lateforecast Jun 1, 2021
  • Construction end2 months lateforecast Jan 28, 2022