Whiskey Jack Nordic Ski Club Society - Day Lodge
Fort St. John, British Columbia
Federal contribution
$219,778
Federal share40%
of $549.4K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 3, 2020
20212022
Built
Approved 8 weeks before the announcement.
- Program
- Community, Culture & Recreation Infrastructure Stream
- Ultimate recipient
- Whiskey Jack Nordic Ski Club Society
- Construction start
- Sep 7, 2021(actual)
- Construction end
- Mar 31, 2022(actual)
Against the original forecast
- Construction start3 months lateforecast Jun 1, 2021
- Construction end2 months lateforecast Jan 28, 2022
Also in Fort St. John
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 56532 in the federal list. How to read these figures.