Back to projects

Street Upgrading & Paving - Anchorage Road

Conception Bay South, Newfoundland and Labrador

completeHighways and RoadsRNIS
Federal contribution
$286,451
Federal share33%

of $859.2K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 18, 2021
2021
Built

Approved 12 months before the announcement.

Program
Rural & Northern Infrastructure Stream
Construction start
Jul 12, 2021(actual)
Construction end
Aug 10, 2021(actual)

Against the original forecast

  • Construction start5 weeks lateforecast Jun 5, 2021
  • Construction end4 months earlyforecast Nov 30, 2021

Also in Conception Bay South