Sewer System Phase 6A
Parson's Pond, Newfoundland and Labrador
Federal contribution
$266,771
Federal share40%
of $666.9K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJan 15, 2021
20212022
Built
Approved 7 months before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- Town of Parson's Pond
- Construction start
- Sep 28, 2021(actual)
- Construction end
- Jun 6, 2022(actual)
Against the original forecast
- Construction start4 months lateforecast Jun 1, 2021
- Construction end6 months lateforecast Nov 30, 2021
Also in Parson's Pond
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 56850 in the federal list. How to read these figures.