Sewer System Phase 6A

Parson's Pond, Newfoundland and Labrador

completeWastewaterGIS
Federal contribution
$266,771
Federal share40%

of $666.9K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJan 15, 2021
20212022
Built

Approved 7 months before the announcement.

Program
Green Infrastructure Stream
Ultimate recipient
Town of Parson's Pond
Construction start
Sep 28, 2021(actual)
Construction end
Jun 6, 2022(actual)

Against the original forecast

  • Construction start4 months lateforecast Jun 1, 2021
  • Construction end6 months lateforecast Nov 30, 2021