Pumphouse Upgrades
Parson's Pond, Newfoundland and Labrador
Federal contribution
$112,641
Federal share40%
of $281.6K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedFeb 4, 2025
202320242025
Built
Approved 2.5 years before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- Town of Parson's Pond
- Construction start
- May 12, 2025(actual)
- Construction end
- Sep 25, 2025(actual)
Against the original forecast
- Construction start4 months lateforecast Jan 20, 2025
- Construction end7 weeks earlyforecast Nov 14, 2025