Back to projects

New Sanitary Sewer Outfall

Parson's Pond, Newfoundland and Labrador

completeWastewaterCWWF
Federal contribution
$264,951
Federal share50%

of $529.9K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 7, 2016
2017
Built
Program
Clean Water and Wastewater Fund
Ultimate recipient
Town of Parson's Pond
Construction start
May 15, 2017(actual)
Construction end
Aug 18, 2017(actual)

Against the original forecast

  • Construction end3 weeks lateforecast Jul 28, 2017

Also in Parson's Pond