Water and Sewer System Phase 5
Parson's Pond, Newfoundland and Labrador
Federal contribution
$329,653
Federal share50%
of $661.4K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedDec 19, 2016
2017
Built
Approved 4 weeks before the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Town of Parson's Pond
- Construction start
- Sep 11, 2017(actual)
- Construction end
- Nov 15, 2017(actual)
Against the original forecast
- Construction start4 weeks lateforecast Aug 14, 2017
- Construction end2 weeks earlyforecast Nov 30, 2017