Water and Sewer System Phase 5

Parson's Pond, Newfoundland and Labrador

completeDrinking WaterCWWF
Federal contribution
$329,653
Federal share50%

of $661.4K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedDec 19, 2016
2017
Built

Approved 4 weeks before the announcement.

Program
Clean Water and Wastewater Fund
Ultimate recipient
Town of Parson's Pond
Construction start
Sep 11, 2017(actual)
Construction end
Nov 15, 2017(actual)

Against the original forecast

  • Construction start4 weeks lateforecast Aug 14, 2017
  • Construction end2 weeks earlyforecast Nov 30, 2017

Also in Parson's Pond