Paving - Various Streets
St. Anthony, Newfoundland and Labrador
Federal contribution
$126,590
Federal share33%
of $379.7K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 30, 2020
2021
Built
Approved 6 weeks before the announcement.
- Program
- Rural & Northern Infrastructure Stream
- Ultimate recipient
- Town of St. Anthony
- Construction start
- Jun 27, 2021(actual)
- Construction end
- Oct 14, 2021(actual)
Against the original forecast
- Construction start4 weeks lateforecast Jun 1, 2021
- Construction end2 months lateforecast Jul 31, 2021