Water Supply Pumphouse Upgrades

Port Saunders, Newfoundland and Labrador

completeDrinking WaterGIS
Federal contribution
$71,396
Federal share40%

of $179.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 30, 2020
2021
Built

Approved 4 weeks before the announcement.

Program
Green Infrastructure Stream
Ultimate recipient
Town of Port Saunders
Construction start
May 10, 2021(actual)
Construction end
May 31, 2021(actual)

Against the original forecast

  • Construction start3 months lateforecast Feb 15, 2021
  • Construction end2 months lateforecast Mar 30, 2021

Also in Port Saunders

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 56888 in the federal list. How to read these figures.