Water Supply Pumphouse Upgrades
Port Saunders, Newfoundland and Labrador
Federal contribution
$71,396
Federal share40%
of $179.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 30, 2020
2021
Built
Approved 4 weeks before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- Town of Port Saunders
- Construction start
- May 10, 2021(actual)
- Construction end
- May 31, 2021(actual)
Against the original forecast
- Construction start3 months lateforecast Feb 15, 2021
- Construction end2 months lateforecast Mar 30, 2021