Back to projects

New Drilled Well

St. George's, Newfoundland and Labrador

completeDrinking WaterGIS
Federal contribution
$79,375
Federal share40%

of $198.4K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 16, 2020
20212022
Built

Approved 5 weeks before the announcement.

Program
Green Infrastructure Stream
Ultimate recipient
Town of St. George’s
Construction start
Jul 26, 2021(actual)
Construction end
Dec 20, 2021(actual)

Against the original forecast

  • Construction start3 months lateforecast May 1, 2021
  • Construction end3 weeks lateforecast Nov 30, 2021

Also in St. George's

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 56897 in the federal list. How to read these figures.