Improvement of Resource Centre's Electrical and HVAC systems
Federal contribution
$60,477
Federal share40%
of $151.2K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 4, 2021
202120222023
Built
Approved 6 weeks before the announcement.
- Program
- Community, Culture & Recreation Infrastructure Stream
- Ultimate recipient
- Glen Cairn Community Resource Centre
- Construction start
- Sep 27, 2021(actual)
- Construction end
- Dec 19, 2022(actual)
Against the original forecast
- Construction end2 weeks earlyforecast Jan 2, 2023
Also in London
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 57680 in the federal list. How to read these figures.