Announced and approvedJul 13, 2021
Built
Approved 5 months before the announcement.
- Program
- Community, Culture & Recreation Infrastructure Stream
- Ultimate recipient
- Township of Schreiber
- Construction start
- Jul 19, 2021(actual)
- Construction end
- Dec 3, 2021(actual)
Against the original forecast
- Construction start4 weeks lateforecast Jun 21, 2021
- Construction end4 weeks earlyforecast Dec 31, 2021