Stoney Creek YMCA Recreation Facility Rehabilitation and Expansion
Federal contribution
$1.4M
$1,361,800
Federal share40%
of $3.4M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 4, 2021
today
2021202320252027
BuiltForecast
- Program
- Community, Culture & Recreation Infrastructure Stream
- Ultimate recipient
- YMCA of Southwestern Ontario, Stoney Creek YMCA
- Construction start
- Jul 14, 2021(actual)
- Construction end
- Mar 31, 2027(forecast)
Also in London